Thursday, January 11, 2007

Project Update 1/11/07

My routers have arrived and I'm pushing out images to the desktops. This is a slow process because we are replacing the hard drives only. I don't have a duplicator so I have to do the images one at a time. 87 of them have to be done. I'm still trying to get the other things that I need ordered ( waiting on management sign off) and am waiting on Sprint to finish the installation and turn up of my MPLS circuits.

I have 23 more days to get it all done.